Struth, Rhineland-Palatinate – Forest location

In der Gemeinde Pomster bzw. Bauler im Landkreis Ahrweiler planen wir die Errichtung von vier Anlagen auf Gemeindeflächen.

One of the most modern turbines for Struth – The Vestas V 172

The construction and operation of four Vestas V 172 wind turbines is planned at the Struth site. The nominal output per turbine is 7.2 MW and will produce an annual amount of electricity of 19,300,000 kWh per wind turbine at the site. The Vestas V172-7.2 MW is one of the most modern wind turbines designed for locations with low to medium wind speeds.

The project has been in the approval process since 2024. The application for the first four plants was submitted in September.

They will save around 59,000 tons of CO₂ per year and supply 51,000 people with clean electricity.

Strom-RZ-green.svg
Megawatt total capacity
CO2-Vermeidung_RZ-green.svg
CO₂ avoidance in tons per year
Vorlage-Icons-WordPress6.png
People who are supplied with electricity each year
Facts
Wind turbine
Wind turbine

Vier Anlagen mit insgesamt 28,8 MW Nennleistung

CO₂ avoidance
CO₂ avoidance

59.000 in Tonnen pro Jahr

Capacity
Capacity

Die Anlage wird ca. 51.000 Menschen pro Jahr mit Strom versorgen

Type
Type

Vestas V172

Hub height
Hub height

175m